Monthly Archives: June 2013
Electrical
Kitchen area: when centerpiece ceiling light was originally hung, it was installed off-center and the subcontractor had to come back and correctly center it. The kitchen table light was installed on a 3-way switch so it could only be turned … Continue reading
Cabinets – kitchen, bathrooms, basement bar, etc. – June 2013 – January 2014
Almost all cabinet doors/drawers (bathrooms, kitchen, basement bar, etc.) throughout the house were replaced three times. Email to Builder 8/20/2013 – Hello Tom, Timberlake’s rep stopped by our house yesterday to inspect the cabinets. They have been to our house … Continue reading
Grout work in master bedroom
The grout in the master bathroom cracks every so often and we have to re-apply grout. The pictures below were taken on 5/19/2019 near the bath tub.
Appliances
June 2013 – The kitchen dishwasher installed was not the correct model number as stated in the contract. It was also damaged. It had to be changed. In 2014, 2015 & 2016 – The kitchen refrigerator was changed three times … Continue reading
Basement engineered hardwood flooring – June 2013 to 2014
From the beginning, our basement engineered hardwood flooring had visible issues. It became clear after two years that the contractor did not install a moisture barrier and did not use the glue “Mapei Ultrabond ECO 995” as he had stated. … Continue reading
First and second levels – Issues with cracked hardwood flooring
Almost every room had several boards removed and replaced due to installation of cracked boards. Repairs went on for one year. Certain area have been filled with a brown putty substance that cracks.
Garage Door Issues
Installer came to fix the track but was unable to fix it. The track was not squared and the distance between the tracks was not the same (not correctly parallel). Even though we oiled the springs and all other moving … Continue reading